Stoke Mandeville Hospital, Aylesbury

Aligned with the “Greener NHS” programme, our team undertook a comprehensive package of sustainability-focused works, including over-roofing, the installation of Solar Photovoltaic (PV) systems, new energy-efficient lighting, upgraded guttering and eaves, and all associated works.

The building remained fully operational throughout the works, requiring careful coordination and phasing to minimise disruption to South Central Ambulance Service operations.

project information

Client Name : SCAS
Project Value: £665K
Architect: Philips Surveyors
Quantity Surveyor: Philips Surveyors
Duration: 20 weeks